Farm Project 2

 

 

-

-

 

 

-

 

 

-

 

 

With the old office damaged by the fire of 2020 and now being used for project 3 a new office sectioned egg room needed to be born project 2

From the picture you can see its original stature, July 2022 renovations began using Polycoat as our supplier for the floor paint and external wall covering

The roof barges had to be removed, new boarding treated were put in place they meant that the roofing felt could be nailed on the edges

The jacks had to be removed cleaned before being painted with red oxide and a brown top coat

The exterior walls cleaned and repaired with masonrys and batten strips then given two coats of the emulsion type wall covering the marketing info said it would act like an insulator and they were right it did quite significantly.



Office

renovated